An enterprise agreement for Bulla Dairy Foods' Derrimut site in Melbourne's west has been approved with a 4% pay rise and Christmas Day paid at double time and a half, as reported by onnotice.com.au. It isn't a construction agreement. It does land in the stretch of the year when construction public holiday rates hit builders hardest: the push to get a slab down before the break, the Christmas shutdown, and the client who wants the keys by New Year.
So this piece isn't about dairy. It's about what the deal says about how labour costs move, and how to make sure the movement shows up in your quotes, not in your margin.
Two ways wages move, and only one is on a calendar
Pay in Australia moves through two separate channels, and builders tend to watch only the first.
- The annual wage review. Each year the Fair Work Commission sets a rise to modern award minimums, which normally applies from the first full pay period on or after 1 July. You can plan for that one.
- Enterprise agreements. A business negotiates its own rates with its workers, on its own schedule. The Commission only approves an agreement if employees are better off overall than they would be under the relevant award. That's how a single site ends up with a 4% rise and its own Christmas Day rate.
The second channel matters to you even if you've never signed an agreement. Your labourers and apprentices live in the same suburbs as factory and warehouse workers. When a big local employer posts a solid rise, it changes what people think a fair rate is, and in our experience that shows up in your crew's next conversation about money well before it shows up in any award.
Construction public holiday rates: where to find the real number
Most on-site employees in building fall under the Building and Construction General On-site Award 2020. Plumbers are generally under the Plumbing and Fire Sprinklers Award 2020, and sparkies under the Electrical, Electronic and Communications Contracting Award 2020. If your business has its own enterprise agreement, that applies instead of the award.
Each of those instruments sets its own public holiday loading, and they aren't interchangeable. Don't price from memory or from last year's spreadsheet. The Fair Work Ombudsman publishes a current pay guide for every modern award, with penalty rates and allowances set out in dollars. Check it before you quote any work over the break.
Two rules from the National Employment Standards catch builders out every year:
- If a public holiday falls on a day your employee would normally work and the site is closed, they're still paid their base rate for their ordinary hours.
- You can ask a worker to come in on a public holiday, but the request has to be reasonable, and they can refuse on reasonable grounds.
The holiday calendar this year
Christmas Day 2026 is a Friday and Boxing Day falls on a Saturday. Most states move or add a holiday on the Monday when that happens, but the rules differ by state, so check the Fair Work public holidays list for each state you have crew working in. New Year's Day 2027 is also a Friday.
That means two short weeks back to back. If your program has a pour, an inspection or a handover sitting in either of them, work out now whether it happens before the break, after it, or on a penalty day, and who pays for that choice.
The construction awards also have provisions for an annual close-down over Christmas, with notice requirements. If you're shutting the site, read the close-down clause in your award and give notice the way it says.
What it means for your quotes
Price labour on a loaded rate, not the base rate. The hourly number in your estimate should already carry superannuation (12% from 1 July 2025), workers comp, leave accruals and the allowances your crew is entitled to. A public holiday loading then sits on top of that, not on top of the base.
Put holiday work on its own line. If the program genuinely needs work on a public holiday, show it as a separate item. The client sees the cost of their deadline and can decide whether the keys before New Year are worth it.
Keep GST out of your cost build-up. GST is charged on your price to the client, not on the wages you pay. Build labour ex-GST, add your margin, then add GST once at the end. Mixing the two is how a quote ends up 10% light on labour.
Ask your subbies for updated rates. Their wage rises flow straight into their prices. Get current rates in writing before you lock in any fixed-price job that runs over the break.
Read your delay clauses. If a fixed-price job slips into the Christmas period because of a client variation or a late approval, your contract decides who wears the extra labour cost. Know the answer before the program slips, not after.
If you're still building labour costs by hand, a proper estimate template stops you from rebuilding the loaded rate from scratch every time. Our guide to construction estimating software covers what to look for.
Admin that saves you a dispute later
- Record public holiday hours separately on timesheets. A lump of "38 hours" doesn't prove you paid the right loading on the right day.
- Keep employee records for seven years. That's the Fair Work requirement, and an underpayment claim can reach back years.
- Recheck every rate on 1 July and whenever an agreement changes. Put it in the diary now.
- Make the program visible to the whole crew so everyone knows which days are on and which are off. Our rundown of construction project management software has the options.
A 4% rise and a double time and a half Christmas at a dairy won't change your award. They're a reminder that labour costs move on more than one timetable, and the builders who come through the break with their margin intact are the ones who priced that in.