NCC changes

The Housing Industry Association has called for an overhaul of the National Construction Code. Its argument is that the code has become too complex and is slowing down the delivery of new homes. Whether or not HIA gets its way, NCC changes always end up in the same three places: your quotes, your contracts and the jobs you already have on the go. Here is how to read the push, and what to sort out now so the next round of changes does not come out of your margin.

Why HIA is pushing now

Governments have committed to 1.2 million new homes under the National Housing Accord, and the industry is widely reported to be running behind that pace. HIA has been making the same case for years. Each new edition of the code adds requirements, cost and approval time to every house, and a leaner code would get more homes out of the ground. Its policy positions are on hia.com.au.

The frustration is fair. Under NCC 2022 the minimum energy rating went to 7 stars and the whole-of-home energy budget came in, and together they changed how a lot of standard house designs were specced. Builders who quoted under the old rules and built under the new ones had to absorb that difference or chase it back as a variation.

How NCC changes reach the job site

The Australian Building Codes Board publishes the NCC on a three-year cycle, and the full code is free to read at ncc.abcb.gov.au. Housing sits in Volume Two, and most of the practical detail is in the ABCB Housing Provisions Standard.

A new edition does not switch on everywhere on the same day. Each state and territory adopts it through its own building regulations, often with its own start date, transition period and local variations. In most states the edition that applies to a job depends on when the building approval is applied for, so check your state's transition rules rather than assuming.

That lag is where builders get caught. A job can be quoted under one edition, approved under another and built over twelve months. The client rarely understands why the price moved.

The builder-eye take: stability matters more than size

This gets lost in the debate. A thick code is not what costs a small builder the most. Churn is. Once your standard details are sorted (timber framing to AS 1684, wet area waterproofing, stair geometry), the size of the code matters less, because you are not reading it cover to cover on every job. What hurts is relearning those details every three years, and relearning them differently in each state you work in.

That cuts both ways for HIA's call. A simpler code would help, especially owner-builders and newer builders who have not built forty versions of the same house. But a rewrite is a big change in its own right. It brings a learning curve, new clause references and another transition period to quote through. If governments act on it, the best result for builders is a simpler code that then stays put, with fewer state variations bolted on top.

Getting ahead of NCC changes in your quoting and admin

You cannot control when the next edition arrives. You can make sure it does not land on a job you have already priced.

  • Name the edition in the quote. State which NCC edition and state requirements your price is based on. Then a later change is a clear variation, not an argument. Check how your standard contract handles changes in law, because that clause decides who pays.
  • Watch quote validity around adoption dates. Say your quotes stay open for 90 days and a new edition starts in your state inside that window. Either shorten the validity or price the new requirements in.
  • Quote code-driven extras with GST. A $4,000 upgrade forced by a code change costs a residential client $4,400 once GST goes on. Put it in at that figure from the start so the client is not caught out.
  • Check the geometry every time. Stairs are a good example. Under the Housing Provisions, risers are 115 mm to 190 mm and goings are 240 mm to 355 mm. Two risers plus one going has to land between 550 mm and 700 mm. Our free stair calculator runs those numbers on site in a few taps.
  • Update templates, not individual quotes. When a change lands, fix your standard inclusions and line items once. If that still means editing a dozen spreadsheets, our guide to the best construction estimating software covers what to look for.
  • Keep compliance evidence with the job. Photograph insulation before lining, barrier heights and waterproofing before tiling. If the job's documents and defects are kept together in one place, you can answer "what were we building to?" years later. Our rundown of the best construction project management software compares the options.

The short version

HIA's call is worth backing in principle and watching closely in practice. Until something actually changes, your building surveyor will check the current NCC and your state's variations. Price to them, write down what you priced to, and plan for the next edition so it does not surprise you mid-job.

If you want the calcs on your phone for the next site visit, the free Built Simple app has all 45 calculators, including the stair calculator, with no signup needed.