TL;DR: Under a retention clause, the client or head contractor holds back part of each progress payment, often building up to 5% of the contract sum, as security against defects. A common setup releases half at practical completion and the rest at the end of the defects liability period, which is often 12 months. You get it back on time when you know the release triggers, put the dates in the diary and can show that every defect was closed out. Contracts and state rules both vary, so read your clause before you rely on any of this.
The last five percent of a job is often the hardest money to collect. The work is done, the owner or tenant has moved in, and your retention is sitting in someone else's account waiting on a date nobody wrote down. This guide covers how a retention construction contract Australia-wide is usually set up: the typical terms, what the defects liability period does and doesn't mean, what triggers release, and the record keeping that makes getting paid routine instead of a fight.
It's written for builders and subbies on commercial and larger residential work. It isn't legal advice. Retention clauses are contract terms, and the wording on your job outranks any general guide, this one included.
What retention is and why clients hold it
Retention is money the paying party keeps back from your progress payments as security. If you leave defects unfixed, walk off the job or go under before the end, the client can use that money to put things right without chasing you.
It shows up at every level of the contract chain:
- Principal to head contractor: the owner or developer holds retention from the builder.
- Head contractor to subcontractor: the builder holds retention from the trades, often on similar terms to the head contract.
- Subcontractor to sub-subcontractor: less common, but it happens on bigger packages.
Retention isn't a penalty and it isn't a discount. It's your money, earned for work already done and held conditionally. Treat it that way in your books. If you write it off in your head the day it's deducted, you'll chase it half-heartedly, and half-hearted chasing is how retention ends up never paid.
How a retention construction contract Australia-wide is usually set up
There's no single national rule that sets the retention percentage. The contract does. That said, a few arrangements come up again and again.
The cap. Total retention is often capped at 5% of the contract sum. Some subcontracts ask for more, and some smaller jobs carry less. The cap is negotiable before you sign and almost never negotiable after.
The deduction rate. Two common methods:
- 10% of each progress claim until the cap is reached. The client takes a bigger bite early and then stops deducting.
- A flat percentage of every claim. For example, 5% off each payment for the whole job.
The form of security. Retention doesn't have to be cash. Standard forms such as AS 4000-1997 General conditions of contract, published through Standards Australia, allow security as cash retention, a bank guarantee, or a mix, depending on what the parties fill in. Some clients will also accept an insurance bond.
The release split. A common arrangement releases 50% of the retention at practical completion and the remaining 50% at the end of the defects liability period. Your contract might use a different split or a single release date.
A worked example
Say you've got a $400,000 commercial fit-out (excluding GST) with retention at 10% of each claim, capped at 5% of the contract sum, and a 50/50 release.
- Retention cap: 5% of $400,000 = $20,000
- Claim 1, $80,000: $8,000 held (running total $8,000)
- Claim 2, $90,000: $9,000 held (running total $17,000)
- Claim 3, $60,000: 10% would be $6,000, but only $3,000 more is needed to hit the cap
- Every claim after that: no further retention
- Practical completion: $10,000 released
- End of a 12-month defects liability period: the remaining $10,000 released
Check whether your contract calculates retention on GST-inclusive or GST-exclusive amounts. The wording varies, and it changes the number you should expect back. Retention also feeds straight into your cash flow forecast, so build it into each claim as you go. Our guide to progress claims in construction in Australia covers how to set up claims so the deductions stay easy to track.
The defects liability period: what it is and what it isn't
The defects liability period (DLP) is a contractual window, usually starting at practical completion, during which you have to come back and fix defects the client notifies. Twelve months is common on commercial work. Some contracts use six months, and some use 24 for particular elements.
Subcontractors should watch one trap closely. If the head contract's DLP runs from the date the whole project reaches practical completion, and your subcontract's DLP is tied to that, a trade that finishes early, like the slab or the frame, can wait a long time before its DLP even starts. Read when your clock starts, not just how long it runs.
Two more points matter:
Some contracts extend the DLP for rectified work. If you fix a defect during the period, the contract may start a fresh period for that item. That can push back final release on part of your retention, or all of it.
The DLP doesn't end your liability for defects. It's the period during which the contract gives you the right, and the duty, to come back and fix things. After it ends, you can still be liable under the contract, at common law and under statutory warranties. For residential work in NSW, for example, the Home Building Act 1989 sets statutory warranty periods of six years for major defects and two years for other defects. Other states have their own schemes. Our guide to construction defect liability in Australia in 2026 covers the longer-term obligations in more depth.
Release triggers: what actually unlocks the money
Retention doesn't release itself. Something in the contract has to happen first, and usually someone has to do something about it. Typical triggers include:
- Practical completion is certified. On a standard form this usually means a certificate from the superintendent or the client. No certificate, no first release, even if the building is occupied.
- The DLP expires. The date is calculated from practical completion, plus any extension for rectified items.
- All notified defects are rectified. Many contracts won't release the final portion while any defect notice stays open.
- A final payment claim is lodged. Some standard forms give you only a short window after the DLP ends to lodge it. Miss that window and you can create a fight you didn't need.
- A final certificate is issued. On superintendent-administered contracts, the final certificate is often the document that triggers return of the remaining security.
Read your clause for deadlines on both sides. The client usually has a set number of days to release security once the trigger happens. You may have a set number of days to claim it. Diary both the day you sign the contract, not the day practical completion is certified.
Residential work is different
On domestic building contracts with homeowners, formal retention is far less common. Most state domestic building laws tie progress payments to defined stages and limit how much a builder can take as a deposit. In practice, the final stage payment does the job retention does on a commercial job: the homeowner pays the last instalment at completion and the builder is still on the hook for defects afterwards.
What builders do run into is an owner holding back the final payment over a list of minor items. That isn't retention unless the contract says it is. Deal with it like any other disputed payment: list each item in writing, fix what's legitimately yours, and keep a dated record of the handover. The rules on what an owner can withhold vary by state, so check with your state's building regulator or your industry association before you push back hard.
Retention trusts and the insolvency problem
Cash retention has a weak point. If the party holding it goes broke, your retention can disappear into the insolvency along with everything else they owe.
Some states have responded. NSW and Queensland both have rules requiring retention money on larger contracts to be held in trust, but the thresholds, the types of contracts covered and the rollout timing have changed more than once. Don't assume a trust protects your money. Ask the head contractor in writing whether your retention is held in trust, and check the current rules with your state regulator.
Ways to reduce the risk:
- Offer a bank guarantee instead of cash. You keep your cash flow and the money isn't sitting in the client's account. The cost is a bank fee and a hit to your facility limit.
- Negotiate a lower cap or an earlier partial release before you sign.
- Don't let retention drift. The longer it sits past its release date, the longer you're exposed to the holder's financial health.
The record keeping that makes release painless
Most retention fights aren't really about money. They're about evidence. The client says a defect is outstanding, you say it was fixed in March, and neither side can prove it. Good records end those arguments before they start.
Keep these for every job that carries retention:
- The signed contract and the annexure showing the retention percentage, cap, release split, DLP length and the form of security.
- A running retention ledger: each claim, the amount held, the running total and the cap. Reconcile it against every payment schedule you receive.
- The practical completion certificate or written confirmation, with the date. That date drives everything after it.
- A defects register: every item notified, the date it came in, who raised it, what was done, when it was closed and who signed it off.
- Dated photos of every defect before and after rectification, stored against the job rather than buried in someone's phone.
- Correspondence: every defect notice, every response and every inspection request, in writing.
- Diary dates for the end of the DLP, your final claim deadline and the client's release deadline.
- For bank guarantees: the original document, its expiry date and the bank's details, so you can get it returned and cancelled.
The defects register does the most work. A month before the DLP ends, send the client a short note listing every defect notified and the date each was closed, with photos available on request. Ask them to confirm nothing is outstanding. That one email turns release from a negotiation into a box-ticking exercise. For a fuller approach to running a register across a job, see our guide to construction defect management.
When the client goes quiet
If a release date passes and nothing arrives:
- Send a written request quoting the clause, the trigger date and the amount, with your records attached.
- Follow up by phone and confirm the call in writing. Sometimes it's just an accounts team that hasn't diarised the date either.
- Consider a payment claim under your state's security of payment legislation. In most states a retention release can be claimed this way, but the time limits and the requirements differ by state. Get advice before you rely on it.
- Get legal advice if the amount justifies it, especially if the client is citing defects you believe are closed.
Act early. Retention claims get harder as time passes, records fade and the people who were on the job move on.
Frequently asked questions
Is 5% retention standard in Australia?
It's common, particularly as a cap on commercial and larger residential work, but it isn't set by law. The contract decides the percentage, the deduction rate and the release split. You can negotiate these before you sign.
Can the client keep my retention if a defect isn't fixed?
Usually, a client can use retention to cover the cost of fixing a defect after notifying you and giving you a reasonable chance to fix it yourself. What they can do, and how much they can keep, depends on the wording of your contract. Respond to every defect notice in writing and promptly, so they can't say you were given the chance and ignored it.
Does the defects liability period end my liability?
No. The DLP is the window the contract gives you to come back and rectify defects. Statutory warranties and other legal obligations can run for years beyond it. In NSW residential work, for example, statutory warranties run for six years for major defects and two years for other defects.
Should I offer a bank guarantee instead of cash retention?
A bank guarantee keeps cash in your business and protects you if the holder becomes insolvent. The trade-off is the bank's fees and the guarantee counting against your facility limit. Make sure the contract states when it must be returned, and keep track of the original document.
Is GST charged on retention?
Retention is part of the contract price, so GST applies to the work it relates to. When that GST is attributed depends on whether you account on a cash or accruals basis and how your invoices and claims are worded. Talk to your accountant so you don't pay GST on money you haven't received yet without meaning to.
Keep the last five percent from slipping away
Retention is usually lost through a missed date or a missing record, not a legal argument. Read the clause before you sign, diary every trigger and keep a defects register you can stand behind. If you're quoting your next job, our construction quote template is a good place to set your payment terms out clearly from the start.