AS 2870 site classification explained

TL;DR: AS 2870 site classification sorts a residential block into one of eight classes based on how much the ground lifts and drops as it wets up and dries out. Class A is sand or rock and barely moves. Classes S, M, H1, H2 and E step up through reactive clay, measured as characteristic surface movement (ys) from under 20 mm to over 75 mm. Class P is the problem bucket: soft soils, uncontrolled fill, landslip, mine subsidence, erosion, abnormal moisture. Classes A through H2 can usually be built off the standard designs in Section 3 of the standard. Class E and Class P go to a structural engineer. Get the soil test before you price the slab, not after you have signed.

Every residential slab in this country sits on an answer to one question: how much is this ground going to move? AS 2870 site classification is how that question gets answered, and it is the single line in a soil report that decides whether your slab is a 300 mm edge beam or a stiffened raft with beams you could lose a wheelbarrow in. Builders get burnt on this constantly, usually in the same way: the slab is quoted off an assumption, the soil test comes back a class or two higher, and the variation conversation happens after the client has already mentally spent the money elsewhere. This guide walks the classes, explains what reactive clay actually does under a slab, covers when a geotechnical report is not optional, and gets specific about how classification flows into cost.

What AS 2870 site classification actually is

AS 2870 is the Australian Standard for residential slabs and footings. It covers houses, townhouses, and most Class 1 and Class 10 buildings under the NCC, and it is picked up by NCC Volume Two through the ABCB Housing Provisions (Part 4, Footings and slabs). AS 1684 covers the timber frame that sits on top. AS 2870 covers what that frame is standing on. If you want the current wording and the adoption dates for your state, the code is free to read at ncc.abcb.gov.au, and the standard itself is purchased separately through Standards Australia. AS 2870-2011 is the edition in force at the time of writing, so confirm the edition your NCC volume calls up before you rely on a table.

The classification is not a soil type. It is a movement prediction. Section 2 of the standard sets out how a site gets classified: a site investigation with boreholes or test pits, soil profiles logged by depth, and a calculated characteristic surface movement value called ys, expressed in millimetres. That ys number is what actually assigns the letter. Two blocks 40 metres apart can classify differently, which is why "the estate is all M" is a story, not a classification.

The classes, A through P, and the numbers behind them

The letters are the shorthand. The ys ranges are the substance:

  • Class A, most sand and rock sites. Little or no ground movement from moisture change. ys effectively 0 mm.
  • Class S, slightly reactive clay. Slight movement. ys up to 20 mm.
  • Class M, moderately reactive clay or silt. ys over 20 mm and up to 40 mm.
  • Class H1, highly reactive clay. ys over 40 mm and up to 60 mm.
  • Class H2, highly reactive clay, high end. ys over 60 mm and up to 75 mm.
  • Class E, extremely reactive. ys over 75 mm.
  • Class P, problem site. No ys range, because the problem is not reactivity.

You will also see M-D, H1-D, H2-D and E-D. The D suffix means deep-seated moisture change, where the ground dries and wets well below the normal seasonal zone. That is common in parts of South Australia and other drier regions, and it changes the founding depth rather than just the beam size.

One detail worth knowing if you are reading an older report: the H1 and H2 split came in with the 2011 edition. AS 2870-1996 had a single Class H covering roughly 40 mm to 70 mm, and Class E above that. If you are working on an extension and someone hands you a soil report from 2004, the class on it does not map cleanly onto today's standard designs. Treat it as history, not as a current classification.

What reactive clay actually does to a slab

Reactive clay swells when it takes up water and shrinks when it dries. The movement is not uniform, and that is the whole problem. If a slab went up and down evenly by 60 mm nobody would care. What happens instead is differential movement: the perimeter of a slab is exposed to rain, garden beds, downpipes and evaporation, while the middle sits under a sealed concrete lid at a fairly steady moisture content.

That gives two classic distortion modes. Edge heave is the perimeter swelling after a wet period while the centre stays put, so the slab dishes. Edge drop, or centre heave, is the perimeter drying and shrinking away, so the slab hogs over its middle. Trees, leaking plumbing and a dry summer following a wet winter all push one way or the other. The design job is not to stop the movement. It is to make the slab stiff enough that the house rides the movement without the brickwork telling everyone about it.

The depth over which this happens is set by climate, and AS 2870 handles it with a depth of design suction change (Hs) that varies by region. It is materially different between coastal New South Wales and Adelaide, which is why a Melbourne rule of thumb travels badly. Take the number from the standard's table for your area, or from the geotechnical engineer who wrote your report.

How AS 2870 site classification drives what the slab costs

Here is the part that hits the quote. Higher class means deeper and more heavily reinforced beams, tighter beam spacing, more concrete, more steel, more excavation, and more spoil to cart. On a stiffened raft the internal beam grid gets closer together as you go up the classes. On a waffle raft the pod depth steps up, with common supplier depths running 175 mm, 220 mm, 300 mm and 375 mm, and the reinforcement goes with it.

Every one of those is a line item that moves:

  • Concrete volume. Deeper beams at closer centres can add several cubic metres on a modest house footprint. Price it per cubic metre delivered, plus pump hire if access demands it, plus GST.
  • Reinforcement. More trench mesh, heavier bar, sometimes a heavier top mesh.
  • Excavation and spoil. Deeper beams are more machine time and more truck movements, and tipping fees are not getting cheaper.
  • Site preparation. Controlled fill, moisture conditioning and a compaction test report where the standard requires one.
  • Engineering. Class E and Class P need a site-specific design, and that is a fee, not a freebie.

Do not carry a slab allowance across from the last job. The honest way to price it is to send the soil report to your concreter and get two numbers back on the actual footprint. If you are building the estimate up properly rather than eyeballing it, estimating software built for Australian jobs will let you swap the slab assembly and see the flow-on to the whole quote in a couple of minutes rather than a couple of hours.

When you need a geotechnical report, and what should be in it

For practical purposes, always. A building surveyor is going to want a site classification before they issue a permit, your engineer needs it to stamp a design, and your builders warranty insurer will want to see it if a claim ever lands. The exception people reach for, classification by local knowledge or a council published map, is allowed in the standard but is a blunt instrument, and it does not protect you when the block turns out to have a filled gully across one corner.

A usable report states, at minimum:

  • The class, including any D suffix.
  • The calculated ys value, not just the letter.
  • The method used and the edition of AS 2870 applied.
  • Borehole or test pit logs with depths and soil descriptions.
  • Depth to founding material and any bearing capacity assumptions.
  • Groundwater observations and the date of investigation.
  • Any Class P triggers found, or a clear statement that none were.
  • Recommendations on site preparation, fill and drainage.

Cost varies a lot by state and by how many boreholes are needed. From talking to builders, a standard single dwelling classification sits in the low hundreds of dollars plus GST, and climbs once you add extra boreholes, a slope stability assessment or salinity testing. Get a quote for your actual site rather than budgeting off a figure in an article, including this one.

Class P: the one that stops a standard design

Class P is not "very bad clay". It is a separate category for sites where the standard's normal assumptions do not hold at all. The triggers include soft clays and silts, loose sands, landslip, mine subsidence, collapsing soils, sites subject to erosion, uncontrolled or undocumented fill, and reactive sites subject to abnormal moisture conditions.

The practical consequence is that the standard designs in Section 3 are off the table. You are into a site-specific design under Section 4, which usually means screw piles, bored piers to a competent stratum, or a suspended slab, and a structural engineer carrying the design. On a sloping block that can pull retaining into scope as well, and the retaining then needs its own engineering and often its own approval. Our guide to retaining wall blocks and when engineering is required covers where that line sits.

Fill is the trigger that catches the most builders, because it is invisible from the footpath. The standard distinguishes controlled fill, placed in layers and compacted to a specified density with test results on file, from uncontrolled fill, which is whatever the last mob pushed over the edge. Broad limits for controlled fill under a standard design run to roughly 800 mm for sand and 400 mm for other material, placed and compacted in layers. Anything deeper, or anything undocumented, and you are having a different conversation. If you are renovating or adding on, this is also where old site works come back to bite, which is one of the reasons extension costs blow out more often than new builds do.

The classification can change after the report is written

A site classification describes conditions at the time of investigation, under normal moisture conditions. Several things on your watch can invalidate it.

Trees. Established trees draw moisture out of clay well beyond their canopy. The standard's guidance works on an influence zone related to mature height, broadly around one times mature height for a single tree and around one and a half times for a group or a row. Removing a big tree is just as much a problem as leaving one, because the soil it had been drying out for twenty years now rehydrates and swells, sometimes for years.

Plumbing. A leaking sewer or storm water line under a reactive slab is an abnormal moisture condition. It is also the most common root cause behind slab movement claims that get argued about five years after handover.

Drainage and landscaping. Garden beds hard against the slab edge, downpipes discharging to ground, no falls away from the building, a paved area that traps water. All of these change the moisture regime the design assumed.

AS 2870 includes an appendix written for homeowners on foundation maintenance and footing performance, and it is worth handing to your clients at handover. It sets out the watering, drainage and planting habits that keep the design assumptions true. Giving it to them is cheap. Arguing about it later is not.

What goes wrong on site, and how it shows up later

Movement shows up as cracking in the masonry and in internal linings, and AS 2870 has an appendix that classifies damage so everyone is arguing about the same thing. In broad terms, hairline cracks under 0.1 mm are negligible, fine cracks under about 1 mm are very slight, cracks up to about 5 mm are slight, 5 mm to 15 mm is moderate, and 15 mm to 25 mm is severe, with the number and grouping of cracks mattering as well as the widest one.

That table is the reason the same crack gets called "normal settlement" by one party and "a structural defect" by another. Record it properly: photograph with a scale, note the width, note the date, note the location on a plan, and note the weather conditions. Handled as a documented defect item rather than a phone call, it stays a technical discussion. Our defect management guide has the process for logging and closing these out with a paper trail that holds up.

The mistakes that cause it are boring and preventable: pouring on a class the design did not cover, cutting beam depth to save concrete, backfilling against the slab with the wrong material, no articulation joints in a long masonry run on a reactive site, and site drainage left to the landscaper who arrived after you left.

Frequently asked questions

Can I use the classification from the block next door?
No. Classification is per site, and the standard's investigation requirements exist because blocks in the same street routinely differ. Neighbouring reports are useful context for what you might be walking into, and they are handy when you are pricing a job at tender stage, but they do not satisfy a building surveyor and they will not help you if something moves.

What is the difference between Class H1 and Class H2?
Only the ys band. H1 is over 40 mm and up to 60 mm of characteristic surface movement, H2 is over 60 mm and up to 75 mm. Both are highly reactive clay. The practical difference is in the standard design you can take off the shelf: H2 asks for a stiffer slab than H1, which means more concrete and steel. If you are reading a pre-2011 report that just says "H", it predates the split and should not be mapped to either.

Does a Class P site always need piling?
No. Class P means the standard designs do not apply and an engineer has to design for the specific problem. The answer might be screw piles or bored piers to a competent layer, but it might also be removing and replacing uncontrolled fill with documented controlled fill, or a raft designed under Section 4 for the conditions found. The engineer decides based on what the report actually shows.

Who is allowed to classify a site?
The standard requires the classification to be done by a suitably qualified person, which in practice means a geotechnical engineer or an engineering geologist working to AS 2870 Section 2. In some jurisdictions and for some insurers there are additional registration requirements. Check what your building surveyor and warranty insurer will accept before you book the cheapest option you can find.

When should I do the soil test in the job sequence?
Before you price the slab and before you sign a fixed price contract. A soil test ordered after contract signing turns every classification surprise into a variation conversation, and variations at that stage cost you goodwill as well as money. If the client will not pay for a soil test up front, price the slab as a provisional sum with the assumed class stated in writing, and make the assumption visible in the contract rather than buried in your own spreadsheet.

Get the classification in front of the numbers

The pattern behind almost every slab cost blowout is the same: a class assumed, a quote issued, a report received, and an awkward phone call. Order the soil test early, price the slab off the class that is actually written on the report, and put the assumption in writing whenever you have to price before you know.

If you want the take-offs, the quote and the site records living in one place instead of across three spreadsheets and a group chat, the Built Simple app is free to download on iOS and Android, and the calculators work on the phone with no signup. Have a play with it on the next job you are pricing and see whether the slab numbers come together faster.