How to Track Costs and Budgets in Built Simple

How to Track Costs and Budgets in Built Simple: Complete Financial Control

Built Simple tracks job costs against the budget you priced in your estimate. Costs come in from purchase orders, expenses and supplier invoices you enter by hand, and your crew’s timesheets, and the job’s live profit and loss updates as they land. This guide walks through the real steps in the web app, from the estimate budget to the final P&L export.

Setting Up Cost Tracking

Where Costs Live (Web App)

There is no separate cost module to switch on. Each job’s budget and actuals sit on its estimate, in the Costings tab. Open Estimates in the sidebar, pick the estimate, then open Costings. You will find:

  • Your categories and line items, with Units, Unit Cost, Markup %, Sub total, Cost with Margin, GST Inclusive and Budgeted Price
  • The Review ribbon, with POs, Variations, Financials and Export P/L
  • Show Actuals, which adds spent and forecast columns beside each line
Set Your Labour Rates

Labour cost comes from timesheets, so set rates before the job starts. In Team Tracker settings, open Employees and set each person’s Hourly Rate (charge-out), superannuation and any Custom rates. The Rates & Costs tab holds the Overtime cost multiplier used for job costing, and the Work Type tab lets you set a cost multiplier per type of work.

Budget Creation

From Estimate to Budget

Your budget is the estimate. Every line you price in Costings carries a Budgeted Price, and that is what actual costs are measured against.

  1. Build the estimate in Costings with Add Category and Add Item, or bring lines in with Add From Library, Add from Catalog or a saved template (see How to Create Professional Estimates in Built Simple)
  2. Set a Markup % on each category, or use Apply Markup to All
  3. Send the quote to your client for e-signature. Once the quote goes out and is signed, the costings lock, so the priced budget becomes your baseline
  4. Later changes to scope go through Variations rather than edits to the locked lines. Review & unlock re-opens the costings if you genuinely need to correct them
Budget Structure

Budgets follow the categories you set up in the estimate, for example Site Works, Framing or Plumbing. Job Financials then reports spend By cost category, so the structure you price in is the structure you track against. Keep categories meaningful from the start.

Recording Actual Costs

Click Show Actuals on the Costings tab. Each line gains Spent to Date, Finalised, Add Expense, Forecast to Spend and Let in Gain/Loss (Excluding margin) columns. Costs reach those columns three ways.

Purchase Orders
  1. In the Review ribbon, click POs, then New PO
  2. Choose the Supplier, add the supplier email and pick the Cost line it belongs to
  3. Add a description and the Accepted price (ex GST)
  4. Tick Email the PO to the supplier now (PDF attached) to send it straight away and click Create & send, or click Create PO to save it without sending

You can also raise one from a line’s row actions with Raise purchase order. Open purchase orders show as Committed (POs) in Job Financials, so you can see money you have promised before the bill arrives.

Manual Expenses and Supplier Invoices

For a receipt or supplier invoice, click Add in the Add Expense column on the line. Choose Manual Entry, fill in Description, Amount (Inc. GST), Date, Payment Method, Reference and Notes, then click Add Expense.

Labour Costs
  • Timesheets your crew log flow into the job automatically and show as Labour (timesheets) in Job Financials
  • Hours count as soon as they are logged, approved or not, so review timesheets regularly
  • Overtime is costed with the multiplier set in Team Tracker settings

Real-Time Cost Monitoring

Job Financials

Click Financials in the Review ribbon to open Job Financials. The same view appears as Live job P&L on the estimate’s Money tab. It shows:

  • Contract value
  • Committed (POs)
  • Spent to date
  • Forecast cost
  • Projected profit and Margin
  • Labour (timesheets)
  • Spend By cost category

The Money tab also summarises lines as Under Budget, Over Budget and Net Variance, so overruns stand out without a spreadsheet.

Dashboard Views

Across all your jobs, the Job P/L Status tile on the dashboard flags jobs that need attention, including a warning when what you have claimed is running behind the work done.

Variation Management

Client Variations
  1. On the Costings tab, open Variations from the Review ribbon
  2. Click New Variation and enter a Title and a Reason / note
  3. Add lines. Use Link to line (optional) when a line changes something already in the estimate, then enter Description, Cost, Markup and Price (ex GST). Click Add line for more, then Create
  4. Click Send to client. The client e-signs from the emailed link, and the variation shows Awaiting client sign-off until they do
  5. If the client agrees or declines some other way, use Record approval or Record decline

Approved variations are added to the budget. The summary at the top shows Original contract, Approved variations and Combined total, so the contract value is always current. For more on keeping changes under control, see our guide to scope creep and variation management.

Invoicing

Invoicing from Built Simple is on the roadmap. Until it launches, raise invoices for progress payments in your accounting software. Check Job Financials first, so each claim lines up with what has been spent and what your client has signed in variations.

Financial Reporting

Export P/L

Click Export P/L in the Review ribbon to export the job’s profit and loss as a PDF or Excel file, for your accountant, your bank or your own month-end review.

Integration Features

Xero
  • Payroll: approved timesheets go to Xero as draft timesheets. Use Push approved to Xero on the Team Tracker overview, or Settings, then Xero Payroll, then Push timesheets
  • This runs in the web app
  • Pulling supplier bills from Xero onto a job is coming soon. MYOB and QuickBooks are on the roadmap, as is invoicing
Keep Bank Records Separately
  • Check logged costs against your supplier bills
  • Reconcile bank transactions in your accounting software
  • Manage cash coding and bank rules in your accounting software

Best Practices

Daily Habits
  • Log manual expenses the day they happen
  • Raise a purchase order before you order, not after the bill arrives
  • Check new timesheets
Weekly Reviews
  • Check every supplier invoice has been logged against its cost line
  • Open Job Financials on every active job
  • Chase variations still awaiting client sign-off
Monthly Analysis
  • Export the P/L for each active job
  • Compare Forecast cost against the Contract value
  • Look for categories that keep running over budget and adjust your next estimate

Common Mistakes to Avoid

  • Delayed cost entry: the P&L is only as current as the last cost logged
  • Wrong cost line: a bill assigned to the wrong line hides an overrun somewhere else
  • Missing receipts: small purchases add up
  • Ignoring variations: agreeing a change on site without a signed variation
  • Unreviewed timesheets: hours count before they are approved

Frequently Asked Questions

Where do I see whether a job is making money? Open the estimate, go to Costings and click Financials in the Review ribbon, or open the Money tab. Job Financials shows the contract value, committed purchase orders, spend to date, forecast cost, projected profit and margin.

How do I log supplier invoices against a job? On the Costings tab, click Show Actuals, then Add in the Add Expense column on the right cost line. Choose Manual Entry, enter the amount including GST, the date and the invoice reference, then click Add Expense.

Does Built Simple forecast cash flow? Not today. Job Financials shows forecast cost and projected profit for each job, but there is no cash-flow forecast across jobs in the app.

Do timesheets count towards job cost before they are approved? Yes. Logged hours flow into the job’s labour cost as soon as they are entered, so review timesheets regularly to keep the P&L accurate.

Need Help?

  • Email: [email protected]
  • Phone: +61 3 7303 3694, Monday to Friday, 9am to 5pm Melbourne time

Related Reading

Looking for the full picture? Check out our guide to the best construction scheduling software in Australia for 2026, including detailed comparisons of Gantt features, mobile apps, and pricing.

Looking for the right tool?

Compare the best construction estimating software for Australian builders in our 2026 guide: covers digital takeoffs, assemblies, AS standards, and pricing for builders of every size.

Built Simple construction software logo

Try It Today

Get started for free. Add your whole team as your needs grow.

  • ©2025 BuiltSimple. All Rights Reserved.
Call 03 7303 3694 Text 0485 028 458